Johnson’s rule: identify the optimal sequencing of these jobs.

Using the Johnson’s rule, identify the optimal sequencing of these jobs. The jobs must go through the machines in the same order starting with the sanding machine.

Johnson’s rule: identify the optimal sequencing of these jobs

CASE 4: SHORT-TERM SCHEDULING
Stan’s Furniture Refinishers has 7 items of furniture to sand first and then varnish using the sending and varnishing machines, respectively. The items and their times on these two machines are shown in the table:

Item                       Sanding time, hrs.              Varnishing time, hrs.
A                                             8                                              7
B                                             6                                              4
C                                             5                                              8
D                                             8                                              12
E                                             10                                           14
F                                             12                                           8
G                                             4                                              6

Questions.
Using the Johnson’s rule, identify the optimal sequencing of these jobs. The jobs must go through the machines in the same order starting with the sanding machine.

 

Identify the cumulative flow time for the initial sequencing and for the sequencing based on the Johnson’s rule. Provide the existing sequence chart and Johnson’s rule charts.

 

Compare and explain your results.

 

More details;

 1.    What is Johnson’s Rule
Johnson’s Rule is a technique that can be used to minimise the completion time for                   a   group of jobs that are to be processed on two machines or at two successive work                   centres.

 

2.    Objectives of Rule
         The Objectives of the Johnson’s Rule are:

To minimise the processing time for sequencing a group of jobs through two work centres.
Minimise the total idle times on the machines.
To minimise the flow time from the beginning of the first job until the finish of the last job.

3.    Conditions for the Rule
In order for the technique to be used, several conditions must be satisfied:

Job time(including setup and processing) must be known and constant for each job at each work centre.
Job times must be independent of the job sequence.
All jobs must follow the same two-setup work sequence.
Job priorities cannot be used.

Attachments

Click Here To Download

The post Johnson’s rule: identify the optimal sequencing of these jobs appeared first on Bestchoice Writers.

Johnson’s rule: identify the optimal sequencing of these jobs

Calculate Price


Price (USD)
$

Why Choose Us For Your Assignment?

Privacy

We value all our customers' privacy. For that reason, all information stays private and confidential and will never be shared with third parties.

Punctuality

With our service you will never miss a deadline. We use strict follow-ups with our writers to ensure that all papers are submitted on time.

Authenticity

We have no tolerance for plagiarism. All papers go through thorough checking to ensure that no assignments contain plagiarism.

Money Back

You feel unsatisfied with your results? No worries. We offer refunds to our customers if any paper is not written according to the instructions.

Clients Love Us

Client #121678
Client #121678
Read More
This is by far the best I have ever scored in a custom essay. I am surprised the writer handled this assignment so well despite the short notice. I will definitely use your service next time.
Client #21702
Client #21702
Read More
When I was recommended to you by my friends, I wasn't sure you could deliver excellent results for Masters research papers until I submitted my first order. I am all yours now.
Client #20730
Client #20730
Read More
Excellent Services! You are the only assignment helper I can rely on. I have worked with many before and your services are exceptional. I have recommended you to my friends and the results are similar.
Client #20387
Client #20387
Read More
I rarely write reviews online but your services are worth promoting. My paper was so urgent I was sure I was gonna miss the deadline but you turned things around. You are awesome!
Client #20189
Client #20189
Read More
I am a satisfied customer. I know I should have given a 5 star because you deserve it but I will give 4.6 because I almost missed a deadline because of a revision. Luckily it was minor and the writer acted promptly.
Client #20187
Client #20187
Read More
Great paper but there is still some room for improvement. I am impressed by your fast responses and how you tacked my concerns professionally. Thank you for being among the few genuine essay writing service providers.
Client #19783
Client #19783
Read More
I can't thank you enough for being a great part of my college life. I recommended you to two more of my friends. I am sure they will be making their orders soon. I love the fact that you offer free pages for referrals. I will be referring a few more and maybe I won't have to pay for my next two paper, LOL.
Previous
Next